USO

USO Activities: At a glance (As on 30.06.2023)-

Sl. No. Activity Name of IP/USP Effective Date Expiry Date Number Installed Physical Verification done Remarks
2019-20 2020-21 2021-22 2022-23
1 National Optical Fiber Network (Bharat Net)-(BBNL)  BBNL  25.02.2014  24.02.2020 17823 (GPs) 219 xxx 638 xxx The work for physical verification was assigned to this office. As per 5% critiria, total 891 sites were to be physically verified. Total 921 sites ensuring to cover all districts have been physically inspected. 
2 LWE Project extended  BSNL  30.09.2014  30.04.2023 78 1 24 11 xxx All Claims in r/o OPEX –T & NT upto March-2021 have been settled and paid to USP. Further, subsidy period was extended by USOF HQ till 30.04.2023. Accordingly, BSNL has submitted their OPEX claims for the Q.E. Mar-2023 and same has been settled. All physical verification has been completed. 
3 Wi-Fi Hotspot (25000)                1442 sites is to be commissioned in UP(E) area BSNL  09.06.2017 31.12.2022 1442 28 75 28 xxx Minimum criteria of 5% of total commissioned sites ensuring to cover all districts have been achieved. CAPEX -100% claims upto Q.E. Dec-2019 has been settled and paid to BSNL. OPEX claims upto Dec-2022 has been received and settled and paid to BSNL.
4 Setting up of Wi-Fi Hotspots at (200) as Pilot Project. 50 sites is to be commissioned in UP(E) area. BSNL  08.11.2017  07.11.2020  25 xxx 25 xxx xxx 1. In UP (E) circle, total 50 sites were to be commissioned. The total cost of CAPEX of 50 sites of UP (E) circle is 2,25,00,000/- and this office had paid 1,12,50,000/- to M/s BSNL as 50% mobilization advance for 50 sites. As per agreement, on commissioning of 50% sites USP has to claim for next installment i.e. 40% for total sites. However, BSNL has commissioned only 25 sites in Ghazipur district upto 31.03.2018 and they have claimed 40% CAPEX for only 25 sites instead of 50 sites. Since, the roll out period has already lapsed and BSNL has not commissioned the left 25 sites, hence, the advance payment already made Rs. 1,12,50,000/- stands adjusted against the full cost of 25 sites installed so far. BSNL has been written.                                                                                                                                                                                                                  2. Further, BSNL has submitted OPEX claim from June-2018 to March-2019 without all required documents. This office has called for the remaining documents. However, BSNL has not submitted the documents as of now.                                                           
5 Wi-Fi Choupal (5000)         1332 sites is to be commissioned in UP(E) area e-CSC 31.03.2017  30.03.2020  1248 10 14 22 17 This office has been phycially verified 63 sites ensuring to cover 01 site in all districts. No role for Fund Disbursement Agency was assigned to this office. All CAPEX payment was done by USOF HQ. OPEX had to be borne by USP own self.   
6 Setting up of Wi-Fi Hotspots (200) at Rural Railway Stations as Pilot Project.                  59 sites is to be commissioned in UP(E) area  Railtel Corporation of Indian Ltd.  18.09.2017  17.09.2020  59 xxx 38 xxx xxx As per guidelines minimum 5% of commissioned sites ensuring to cover 01 site in each district have been completed. Total 38 sites have been physically verified. All claims (50% Mobilization advance & 40% Second Installment) received in this office has been settled. Further, M/s RailTel has submitted their claims for 10% CAPEX (Last Installment), 10% Centage and OPEX claim from Q.E. June-2019 to Dec-2020. All the above claim has been settled.
7 354 uncovered villages mobile tower by RJIO RJIO 28.04.2020 27.01.2031 6 xxx xxx xxx 4 Subsidy claim in r/o Front Loaded Subsidy for all 06 sites have been settled and paid to M/s RJIL. Subsidy Claims in r/o Equated Quarterly subsidy upto Q.E. Dec-2021 has been settled and paid to the USP. Further,  EQS for the QE Mar-23 has received and the same will be settled after verification of EQS claims by the TPA/LSA.
8 4G based Mobile Services in identified uncovered villages in Aspirational Districts RJIO 17.03.2021 16.03.2032 19 xxx xxx xxx xxx M/s RJIL had claimed for FLS & EQS for 09 sites after quarter ending March-2022 wherein 02 sites are commissioned in Q.E. Sept-21, 04 sites in Q.E. Dec-21 & 03 sites in Q.E. March-22. All FLS claims have been settled and paid to the USP. Further, after quarter ending June-2022, the USP has submitted FLS claim for 04 sites. Claim has been settled and paid to the USP. Further,  EQS for the QE Mar-23 has received and the same will be settled after verification of EQS claims by the TPA/LSA.
9 O&M, FLM for BharatNet-Ph-I&II BSNL  01.07.2022 30.06.2023 xxx xxx xxx xxx xxx The advance EQS claim w.r.t. Fiber Leasing and OLT space & Misc. Infra. Charges for QE June-2023 has received and same are under process. O&M claims w.r.t. AMC charges and One time cost for repair of GP are also under process.
10 LWE Project-Phase-II BAL 01.10.2021 28.03.2033 xxx xxx xxx xxx xxx The scheme is under rollout pediod. As per agreement, rollout period is 18 months from the effective date
11 Saturation 4G mobile services in uncovered villages BSNL  27.07.2022 13.12.2028 xxx xxx xxx xxx xxx The scheme is under rollout pediod. As per agreement, rollout period is 500 days from the effective date
Total 19867 258 176 699 21  

 

Details of Subsidy claimed, disbursed and recovery as on 30.06.2023: 

Sl. No. Activity 2021-22 2022-23 2023-24 Remarks
Claimed Settled Recovery Claimed Settled Recovery Claimed Settled Recovery
LD Penalty Other Recoveries LD Penalty Other Recoveries LD Penalty Other Recoveries  
1 LWE Project Extended Period  11089321 56031601 0 5531087 15506809 129482228 129482228 0 26328361 0 16941600 16941600 0 6068430 0 (i) Subsidy deibursement period upto Q.E. March-2021 was compledt and all the claims have been settled. Further, as per extension period, M/s BSNL has submitted the EQS claim for the Q.E. March-2023 and the same has been settled and net amount paid to BSNL.
2 Wi-Fi Hotspot (25000)                      1442 sites is to be commissioned in UP(E) area 28426818 96365033 0 75735432 0 10302725 10243962 0 773206 0 7330565 7330565 0 0 0 (1) The submsidy period has expired  of all the sites in QE Dec-2022 and the OPEX claim up to the QE Dec-2022 has been settled. The With held claIm amount from the Q.E. March-2019 to Q.E. Sep-2022 has also been settled after receipt the confirmation of with held sites location from USOF HQ.                                
3 Setting up of Wi-Fi Hotspots at (200) as Pilot Project. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0  
4 Wi-Fi Choupal (5000)                                0 0 0 0 0 0 0 0 0 0 0 0 0 0 0  
5 Setting up of Wi-Fi Hotspots (200) at Rural Railway Stations as Pilot Project.                                                       59 sites is to be commissioned in UP(E) area  0 0 0 0 0 37529623 37370631 0 255077 0 0 0 0 0 0 All the claims of CAPEX, Centage and OPEX has been settled.
6 354 uncovered vilages mobile tower by RJIO 32243246 5500980 0 0 0 28314675 27326475 1452654 0 0 0 0 0 0 0 (1). Rs. 4842180/- in r/o FLS and Rs. 247050/- in r/o EQS for Q.E. Dec-2020 was claimed in FY-20-21. Rs. 29053080/- in r/o FLS (CAPEX) and Rs. 3190166/- in r/o EQS from Q.E. Mar-2021 to Dec-2021 was claimed in FY-2021-22. Rs. 2621475 in r/o EQS from Q.E. March-2022 to Dec-2022 was claimed in FY-2022-23  
(2).  Rs. 4842180/- in r/o FLS against 01 site for Q.E. Dec-2020 & Rs. 658800/- in r/o EQS claim QE Dec-22 has been settled. Further,  EQS for the QE Mar-23 has received and the same will be settled after verification of EQS claims by the TPA/LSA.
7 502 Uncovered Villages 0 0 0 0 0 121726255 95192755 0 1163 26533500 0 0 0 0 0 Rs. 8,40,22,750/- in r/o FLS against 19 sites was claimed in FY-2022-23. 
Rs. 8,40,22,750/- in r/o FLS against all 19 claimed sites have been settled and paid to the USP. The EQS claim QE Dec-22 has been settled. Further,  EQS for the QE Mar-23 has received and the same will be settled after verification of EQS claims by the TPA/LSA.
8 O&M, FLM for BharatNet-Ph-I (Phase-1 & Phase-II sites)   0 0 0 0 641914410 218603526 0 0 0 348224391 313415753 0 27205670 108384547 The advance EQS claim w.r.t. Fiber Leasing and OLT space & Misc. Infra. Charges for QE June-2023 has received and same are under process. O&M claims w.r.t. AMC charges and One time cost for repair of GP are also under process. Some amount of mobilization advance has to be adjusted from the claim of QE March-23. Some amount of mobilization advance has to be adjusted from the claim of QE March-23. During the fillingh OSR-2 of claims for the QE March-2023 some issues are being faced. During the filling of Mobilization advance amount in the Adjustment Particular (2A) colomn, the activities are not showing in that colomn.
TOTAL 71759385 157897614 0 81266519 15506809 969269916 518219577 1452654 27357807 26533500 372496556 337687918 0 33274100 108384547